Bricklayer hospitalised for a month after fall through collapsing roof
- Oldham-based company fined £30,000 after Health & Safety Executive investigation found multiple failings
- 25-year-old bricklayer sustained serious injuries including fractures to his right leg, hip and left hand
- Latest HSE statistics show falls from height remain the leading cause of fatal injuries in the workplace
An Oldham-based construction company has been fined after a bricklayer was hospitalised for a month when the floor he was working on collapsed.
On 4 June 2024 at a house under construction on Lynn Street, Oldham, the 25-year-old was bricklaying on the upper level of a house when the floor he was working on collapsed.
The worker fell along with multiple concrete blocks that had been stored on the upper floor. He sustained fractures to his right leg, hip and left hand, requiring surgery and a month-long stay in hospital.
An investigation by the Health and Safety Executive (HSE) found that Oldham Business and Construction Management Limited, as the principal contractor, had failed to properly plan, manage and monitor the construction work on site.
The floor that collapsed had been overloaded with concrete blocks and had not been constructed in accordance with the manufacturer’s design.
The investigation also identified a number of other health and safety failings at the site, including unsafe scaffolding, inadequate arrangements for work at height, a lack of fire alarms and inadequate competent site management.
As a result of these failings, HSE inspectors issued multiple enforcement notices.
HSE guidance states that effective management of health and safety is crucial to the successful delivery of a construction project. Principal contractors have an important role in managing the risks associated with construction work and must plan, manage and monitor the construction phase, ensuring that effective preventative and protective measures are in place and that appropriate supervision is provided.
HSE has a range of guidance on managing health and safety in construction available online.
Oldham Business and Construction Management Limited, of Bath Street, Oldham, pleaded guilty to breaching Regulation 13(1) of the Construction (Design and Management) Regulations 2015. The company was fined £30,000 and ordered to pay £4,883 in costs, to be paid within 3 years, at Warrington Magistrates’ Court on 11 August 2026.
HSE Inspector Karen Farley said:
“The injuries suffered by this worker were the consequence of fundamental failures to manage health and safety.
“Our investigation revealed that this was not an isolated failing but part of a broader pattern of poor health and safety standards across the site.
“The construction industry remains one of the highest-risk sectors and employers must ensure that work is properly planned, supervised and carried out safely.
“This incident was entirely foreseeable and could have been prevented had the floor been constructed in accordance with the manufacturer’s instructions and safe systems of work been in place to ensure it was not overloaded with construction materials.”
The HSE prosecution was brought by HSE Enforcement Lawyer Arfaq Nabi and Paralegal Officer Hannah Snelling.
Further Information
- The Health and Safety Executive (HSE) is Britain’s national regulator for workplace health and safety. We are dedicated to protecting people and places, and helping everyone lead safer and healthier lives.
- More information about the legislation referred to in this case is available.
- Further details on the latest HSE news releases are available.
- HSE does not pass sentences, set guidelines or collect any fines imposed. Relevant sentencing guidelines must be followed unless the court is satisfied that it would be contrary to the interests of justice to do so. The sentencing guidelines for health and safety offences can be found here.